Alabama MasonryDothan PCKrispy KremeBill RobisonKennedy Land & TimberDustin FowlerMPIDMGLloyds WreckerTri-State ParkingFun ZoneSolomonRich RetailsDothan LivestockFlowers HospitalMedia MechanicGreg FaulkDothan PeriodonicsHouse of FlowersCherry & Irwin Personal Injury AttorneysChris MaddoxHardwick FlooringThe Plant




Improvements to SR-123 to begin Wednesday

Matt Boster

Viewed: 2305

Posted by: Matt Boster
Date: Dec 27 2018 11:28 AM

MONTGOMERY- An Alabama Department of Transportation project on SR-123 from the intersection of SR-12 (US-84) to the junction of SR-134 in Newton will begin Wednesday, January 2, weather permitting.


As part of the project, crews will be making safety improvements including, widening, planing, resurfacing and striping in the area.


During construction, lane closures will not occur during peak travel hours.


ALDOT awarded the project to Wiregrass Construction, at a cost of $1,856,879.38 with 40 working days. The project is expected to be complete by April.


ALDOT’s mission is to provide a safe, efficient, environmentally and economically sound transportation network across Alabama.